City of Sacramento pre-approved · 559 sf · 1 bed
Sacramento City 1-Bed (20×30)
Base $195,000 · Upgraded $240,000
Published estimate dated 7/7/2026. Current pricing, utility requirements, agency fees and site conditions are confirmed at the consult.
The plan
Documents and official sources
Estimate, trade by trade
Tap any trade to see its scope and specs, the same detail as our construction contract.
CabinetsUpgrade option: Stain Finish$8,500+$1,000
Furnish and install cabinets. Design will be per cabinet specification document included in contract. Cabinets will be in style/color/features as show on the included quote. Install hardware on all doors and drawers. Install scribe moldings.
| Feature | Choice |
|---|---|
| Supplier | Kitchen Cabinet Distributers |
| Door Style | Brooklyn |
| Door Overlay Style | Partial Overlay |
| Door Material | Maple |
| Cabinet Box Construction | Maple Box |
| Interior Finish | Natural Birch Veneer |
| Hinge Style | Concealed, Soft Close |
| Drawer Slide Style | Undermount, Soft Close, Full Extension |
| Finish | Painted |
| Finish Color | White |
| Countertop Height | 36" (Standard) |
| Countertop to Uppers Clearance | 18" (Standard, Code Minimum) |
| Height to Top of Uppers | 93" |
| Total Uppers Length | ~10ft |
| Total Lowers Length | ~15ft |
| Uppers-Ceiling Trim Style | 3" Crown |
| Kitchen Sink Base Width | 36" |
| Kitchen Sink Mounting Style | Undermount |
| Kitchen Sink Front | Apron Front |
| Bath Vanities | Included with Cabinet Package |
| Bath Sink Base Width | 36" |
| Bath Sink Style | Undermount |
| Add-ons and Features | See cabinet quote for specifics. |
Upgrade: Stain Finish (+$1,000)
Concrete$15,500
Complete all concrete work as shown on plans, to specifications dictated by engineer of record. Includes all landings per plans, or min. required by code. Includes concrete equipment pads for condenser and/or water heater if on exterior of building.
| Feature | Choice |
|---|---|
| Foundation Type | Slab on Grade |
| Foundation Area | 600 sqft |
| Foundation Footer Size | 12" x 12" |
| Foundation Vapor Barrier | 10 MIL Plastic |
| Foundation Reinforcement | #3 rebar, 18" On Center each way |
| Foundation Surface Finish | Smooth (not polished) no control lines |
| Flatwork Area | 30 sqft |
| Flatwork Surface Finish | Broom Finish |
| Post Footings | (1) 24" square |
| Piers | None |
Countertops$5,500
Furnish and install countertops. Countertops will be installed on all cabinets bought in the cabinet package. Countertops will not be installed on third-party cabinets (like integral sink bath vanities).
| Feature | Choice |
|---|---|
| Countertop Area | ~30 sqft |
| Material | Quartz |
| Thickness | 2CM |
| Plywood Decking Needed | Yes |
| Surface Finish | Polished |
| Backsplash Included | Yes, 4" in kitchen and bath |
DoorsUpgrade option: Solid-Wood, MDF Veneer$6,000+$2,000
Furnish and install interior and exterior doors as shown on plans. Door design and details per included door quote, and below. Does not include any slider doors (provided under "Windows"). If Water Heater enclosure door is present, it is to be plain panel fiberglass with air ventilation integrated into door.
| Feature | Choice |
|---|---|
| Hinge Color | Black |
| Door Stop Style | Solid, mounted on bottom of door Interior |
| Construction | Full MDF |
| Door Height | 80" |
| Style | 2-Panel |
| Sticking | Square |
| Jamb Size | 4-9/16" Exterior Entry Door |
| Construction | Fiberglass |
| Door Height | 80" |
| Style | Craftsman 1/4 Lite |
| Sticking | Flush Glazed |
| Sidelites | None |
| Jamb Size | 6-9/16" |
Upgrade: Solid-Wood, MDF Veneer (+$2,000)
DrywallUpgrade option: Imperfect Smooth Drywall Texture$8,000+$2,500
Hang drywall on all interior walls. Tape all joints, patch all nail holes and other defects. Light sanding. Add texture style specified below.
| Feature | Choice |
|---|---|
| Wall Thickness | 1/2" |
| Ceiling Thickness | 5/8" |
| Wet-Area Drywall Type | Dens-Glass |
| Interior Corner Detail | Square Corners |
| Drywall Surface Texture | Medium Knockdown |
| Fire-Rated Exterior Walls? | None |
Upgrade: Imperfect Smooth Drywall Texture (+$2,500)
ElectricalUpgrade option: Add Car Charger$13,000+$1,750
Furnish and install all electrical as shown on plans. Install per electrical code. Dimmer switches only installed where mandated by code, all other switches will be on/off paddle type. Include humidistat as needed by code in wet areas. All receptacles to be tamper-resistant. Includes nail plates as needed. Includes coordination with local utility to complete service upgrade paperwork if required.
| Feature | Choice |
|---|---|
| Utility Feeder Style | Overhead |
| Utility Feeder Upgrade | None |
| Utility Feeder Wire | N/A |
| Additional Meter | No |
| Metering Configuration | Use Existing meter configuration |
| Existing Primary Panel | No Work Needed |
| New Building Panel Feed | Existing panel Sub-breaker |
| New Building Panel Size | 125A |
| New Building Panel Location | Exterior Mount |
| New Building Panel Feeder Wire | Aluminum |
| Light Switch Style | Non WiFi, Dimming where required by code |
| Low Voltage Conduit Underground | Yes, 1" with pull string |
| Low Voltage Drops | (1) 3/4" flex drop |
| Door Bell/Chime Wiring | Included |
| Range Circuit | (1) at 50A 240V |
| Washer/Dryer Circuit | (1) at 30A 240V |
| Water Heater Circuit | (1) at 30A 240V, Including disconnect |
| HVAC Circuit | (1) at 30A 240V, Including disconnect |
| Car Charger Circuit | None |
| Uefer Ground in Foundation? | Included |
Upgrade: Add Car Charger (+$1,750)
ExcavationUpgrade option: 100ft Extra Trenching$4,500+$2,000
Provide labor tools and materials required to complete any excavation needed per plans. Includes cost to off-haul material if needed.
| Feature | Choice |
|---|---|
| Saw Cutting | ~20ft |
| Saw Cut Patching | Concrete |
| Trenching and Backfill | ~100ft |
| Dig Foundation Footers | 12"W x 12"D strip footings |
| Piers Drilling | None |
| Grading | None |
| Gravel Delivery | Base for slab on grade foundation |
Upgrade: 100ft Extra Trenching (+$2,000)
FixturesUpgrade option: Contractor Supplied Appliances (Samsung)$4,500+$10,000
Scope detail in the full contract.
Upgrade: Contractor Supplied Appliances (Samsung) (+$10,000)
FlooringUpgrade option: Engineered Hardwood Flooring$4,200+$1,500
Clean and prepare subfloor to prepare flooring. Use self leveling compound for any defects over 1/8" in the flooring. Install flooring per manufacturer's instructions, and specifications below.
| Feature | Choice |
|---|---|
| Floor Type | Luxury Vinyl Plank |
| Underlayment Type | Per Manufacturer Recommendation |
| Install Method | Floating |
| Material Allowance | $3/sqft Kitchen Flooring |
| Floor Type | Same as Main |
| Underlayment Type | N/A |
| Install Method | N/A |
| Brand/Model/Color | N/A |
| Material Allowance | N/A Bathroom Flooring |
| Floor Type | Tile |
| Underlayment Type | N/A - See Tile Scope |
| Install Method | N/A - See Tile Scope |
| Brand/Model/Color | N/A - See Tile Scope |
| Material Allowance | N/A - See Tile Scope |
Upgrade: Engineered Hardwood Flooring (+$1,500)
Framing$12,000
Frame building according to plans and engineering calculations. Includes purchase and install of all hardware per plans and engineering. This includes Labor only, materials will be provided under Lumber/Trusses. Includes framing of skylights as shown on plans.
| Feature | Choice |
|---|---|
| Building Height | <16ft, single story |
| Building Shape | Rectangular |
| Building Width | 20 ft |
| Building Length | 30 ft |
| Conditioned Floor Area | 367 sqft |
| Wall Height | 8 ft |
| Wooden Subfloor | None (Slab on Grade) |
| Exterior Wall Framing | 2x6, 16" OC |
| Roof Pitch | 5/12 |
| Roof Framing Style | Cut/Stack |
| Number Valleys | 0 |
| Number Hips | 0 |
| Overhang Width | 12" Gable and Eave |
| Interior Wall Size | 2x4, 16" OC |
| Interior Stairs | None |
| Ceiling Vault | None, Flat Ceiling |
| Attic Access | Attic Access Panel, 22" x 30" |
| Subfloor Access | N/A |
| Decking Sub-Structure | None |
General$6,500
Complete general project tasks relating to overall jobsite logistics and customer experience. Also, tasks needed to complete the project, but not included by other subcontractors/vendors. Item Included Details Includes filling out needed paperwork, printing plans Permit Submission Included as needed, etc. Includes minor changes required by local building Plan Revisions Included department. Does not include major re-designs, or additional engineering Surveyor Not Included Geotechnical Report/Engineering Not Included Porta-Potty Onsite Included Bi-Weekly cleanings Temporary Construction Fencing Not included Subfloor Protection Included Red Rosin paper installed after framing Finished Floor Protection Included Ram Board or similar after finished flooring installed Regular Jobsite Cleanup Included Weekly Material Warehousing and Delivery Included Demo of Existing Structure Not included Special Notes: Includes drafting as needed to submit pre-approved ADU plans. Price: $ 6,500.00 Sacramento Pre-Approved 1-Bed Estimate Sacramento, CA 7/7/2026 - 7:48 AM CSLB Lic# 1098046 © 2022 Redwood ADU
HERS$750
Scope detail in the full contract.
HVACUpgrade option: Super Efficient 24+ SEER Unit$5,500+$1,500
Install Heating, Ventilation and Air Condition equipment as specified below. Head units (if any) shall be installed during rough-in and prior to drywall/paint. Excludes Title 24 report and documents, those will be provided during design/engineering. Includes system start-up and pressure test of lines. Includes
| Feature | Choice |
|---|---|
| System Type | Ductless Mini-Split, Heating and Cooling |
| System Size | 2 Ton, 1 Head Unit |
| System Efficiency | Title 24 minimum, or greater |
| Head Unit/Register Mount Style | Wall-Mount |
| Gas Furnace Included? | No |
| Thermostat Type | Wired and Handheld Remote, no WiFi |
| Range Vent Ducting | Included, 6" Solid |
| Bath Vent Ducting | Included, 4" Flex |
| Dryer Vent Ducting | Included, 4" Solid |
| Install Condensate Line(s) | Included |
| Condensate Pump | None Title24 |
| HVAC Efficiency (Min.) | 14.0 SEER / 8.5 HSPF |
| Duct Insulation (Min.) | None (Ductless) |
| IAQ Exhaust Fan Required | Yes (26 CFM min) |
Upgrade: Super Efficient 24+ SEER Unit (+$1,500)
Insulation$5,000
Install insulation in all locations, minimum R rating to meet or exceed Title 24 report.
| Feature | Choice |
|---|---|
| Floor insulation Value | None (Slab on Grade) |
| Floor Insulation Type | N/A |
| Wall Insulation Value | R-21 (in 2x6 framing) |
| Wall Insulation Type | Faced Fiberglass Batts |
| Attic Insulation Value | R-30 above ceiling |
| Attic Insulation Type | Faced Fiberglass Batts |
| Roof Deck Insulation Value | R-13 |
| Roof Deck Insulation Type | Fiberglass Batts |
| Exterior Insulation Value | None |
| Exterior Insulation Type | N/A |
Lumber$10,500
Provide structural lumber materials for the project. This will include all structural hardware needed, including concrete embedment's. This will include rough deck framing, but not finish decking or railing. Includes delivery to jobsite.
| Feature | Choice |
|---|---|
| Wall Sheathing | 15/32" CDX Plywood |
| Floor Sheathing | None (Slab on Grade) |
| Roof Sheathing | 19/32" CDX Plywood |
| Roof Sheathing On Overhangs | Construction Grade OSB/Plywood |
| Roof Framing Type | Cut/Stack |
| Rafter Size | 2x6 |
| Eave Block Venting | Vented - Holes w/ Screen |
| Exterior Decking Framing | None |
| Roof Fascia Material | 1x_ Hardie Board |
| Exterior Post/Beam Material | Pine (Painted) Title 24 |
| Radiant Barrier on Roof Sheathing | No |
PaintingUpgrade option: Additional Wall Color$8,750+$1,500
Exterior: Paint/stain all exterior walls, window trim and doors (excluding stucco - color is included in stucco mix). Caulk all gaps and seams that require waterproofing. Interior: Prime all drywall walls/ceilings with PVA primer made for drywall. (2) coats paint all walls/ceilings. Light sanding and painting of baseboards, casings, doors, moldings, and window sills. Exterior Paint/Stain Color Sheen Siding/Body Included w/ Stucco Mix Flat Trim/Fascia SuperPaint Exterior Acrylic Latex Low Luster SuperPaint Exterior Acrylic Latex Soffit/Under Eave Low Luster Gable Detail None Front Door Emerald Urethane Trim Enamel Semi-Gloss Storage/WH Doors SuperPaint Exterior Acrylic Latex Flat Deck Framing/Posts SuperPaint Exterior Acrylic Latex Low Luster Interior Paint/Stain Color Sheen Walls SuperPaint Interior Acrylic Latex Satin Ceilings Premium Ceiling Paint White Flat Doors ProClassic Waterborne Interior Acrylic Enamel Semi-Gloss Trim ProClassic Waterborne Interior Acrylic Enamel Semi-Gloss Special Notes: Price: $ 8,750.00 Sacramento Pre-Approved 1-Bed Estimate Sacramento, CA 7/7/2026 - 7:48 AM CSLB Lic# 1098046 © 2022 Redwood ADU
Upgrade: Additional Wall Color (+$1,500)
PlumbingUpgrade option: All-Copper$13,000+$4,000
Includes Rough-in, Top-out and Set/Finish. Includes all piping, fittings and angle stops. Includes rough-in water and washer boxes. Includes Hose Bib fittings. All plumbing will be strapped, plated, and set on test for inspection. Does not include trenching or backfill, but may include minor hand-digging. Does not include purchasing fixtures - those are accounted for under "Fixture" section. Does not include replacement of existing house sewer lateral to street, if city requires replacement.
| Feature | Choice |
|---|---|
| Tie Into Existing Sewer Lateral | Included |
| Water Pipe Material (in Walls) | PEX-A Expansion |
| Water Pipe Material (Exposed, stub-outs) | Copper |
| Water Pipe Material (Underground) | PVC |
| Waste Pipe Material | ABS |
| Exterior Clean-Out | (1) Two-way clean out 18" outside building |
| Sewage Ejector Pump | None |
| Hot Water Pipe Insulation | Included, insulate all hot water piping |
| Refrigerator Icemaker Box | Included |
| Washer Box | Included |
| Shower Valve Style | DELTA brand, single outlet |
| Showerhead Style | Single outlet @ 84"H |
| Water Heater Location | Unconditioned Water Heater Closet |
| Gas Service | No |
| Furnace Gas Line Size | None |
| Range Gas Line Size | None |
| Dryer Gas Line Size | None |
| Fireplace Gas Line Size | None |
| Water Heater Gas Line Size | None |
| Dedicated Hot Water Recirculation Loop | None |
| Recirculation Pump | None |
Upgrade: All-Copper (+$4,000)
RoofingUpgrade option: Presidential Shake$6,000+$2,500
Install new roofing per plans, and spec below. Include all new flashings. Includes all roof jacks for plumbing and ventilation. Includes installation of skylights and skylight flashing as shown on plans. Includes underlayment installation. Include gutters and downspouts shown on plans. Does not include underground drain lines for downspouts.
| Feature | Choice |
|---|---|
| Roofing Type | Asphalt Shingle - Owens Corning Duration |
| Underlayment | Synthetic |
| Flashing Material | Galvanized Steel, painted |
| Venting Style | Ridge Vent |
| Provide and Install Plumbing Jacks | Yes |
| Provide and Install HVAC Jacks | Yes |
| Gutter Style | Fascia |
| Gutter Material | Galvanized Steel |
| Gutter Size | 5" |
| Gutter Guards | Stainless Steel Micro-Mesh |
| Downspout Style | 2" x 3" Rectangular |
| Downspout Material | Galvanized Steel |
| Cool Roof Required | Yes |
Upgrade: Presidential Shake (+$2,500)
Shower GlassUpgrade option: Glass Shower/Tub Sliding DoorsUpgrade only+$1,500
Scope detail in the full contract.
Upgrade: Glass Shower/Tub Sliding Doors (+$1,500)
SidingUpgrade option: 3-Coat Stucco w/ Continuous Foam Insulation$8,500+$3,000
Furnish and install siding on exterior of house.
| Feature | Choice |
|---|---|
| Siding Type | 3-Coat Stucco w/ Acrylic topcoat |
| Siding Detail | Medium Smooth Finish (1 pass finish coat) |
| Trim Type | None |
| Gable Detail | None |
| Belly Band | None |
| Soffiting | None - open eaves |
| House wrap | Included |
| Siding Material Allowance | N/A |
| Window Trim Detail | No Sill |
Upgrade: 3-Coat Stucco w/ Continuous Foam Insulation (+$3,000)
Tile$2,750
Install tile as shown on plans and specified below. Tile choice and layout details will be given by client to tile installer.
| Feature | Choice |
|---|---|
| Floor Tile Type | None |
| Wall/Surround Tile Type | Solid Surface (Quartz) |
| Wall/Surround Tile Height | 80" |
| Wall/Surround Accent Tile | None |
| Tiled Shower Pan | None |
| Shower Pan Tile Type | None |
| Shower Niche | None |
| Shower Niche Tile | None |
| Grout Line Size | N/A |
| Grout Type | N/A |
| Edging Detail | N/A |
| Bath Tile Material Allowance | $ 500.00 Backsplash |
| Tile Type | Quartz - Included with Countertops |
| Grout Line Size | N/A |
| Grout Type | N/A |
| Grout Color/Brand | N/A |
| Edging Detail | N/A |
| Backsplash Tile Material Allowance | N/A |
TrimUpgrade option: Crown Moulding, Cased Window Trim$4,250+$2,500
Install all finish carpentry details on the project. Includes the items listed below.
| Feature | Choice |
|---|---|
| Baseboards | Rounded Edge - 5-1/4" |
| Crown Molding | None |
| Door Casing | Rounded Edge - 3-1/4" |
| Window Trim | Apron and Stool only - drywall return sides and top |
| Trim Material | MDF, FJ Pine in wet areas |
| Trim Finish | Primed |
| Wood Accent Wall | None |
| Closet Shelving | Included, Shelf and Pole full width Interior Stairs |
| Risers | None Treads Handrail Handrail Brackets Balusters |
Upgrade: Crown Moulding, Cased Window Trim (+$2,500)
WindowsUpgrade option: Andersen 100, Colored Options$5,000+$1,250
Install all windows as shown on plans and in window quote. Includes purchase, warehouse, and jobsite delivery of windows.
| Feature | Choice |
|---|---|
| Window Construction | Vinyl |
| Window Brand/Model | Milgard Tuscany |
| Exterior Color | White |
| Interior Color | White |
| Hardware Color | White |
| Grid Design | None |
| Grid Type | None |
| Mounting Style | Nail-Fin (New Construction) |
| Window Setback | 1-3/8" |
| Glass Type | Low-E (standard) |
| Bathroom Obscured Glass | Obscured |
| Window Count | See Plans |
| Skylight Count | None |
| Skylight Brand/Style | N/A Title 24 |
| Window Energy Values | U-0.40, SHGC-0.22 |
Upgrade: Andersen 100, Colored Options (+$1,250)
The upgraded total includes all 15 upgrade options. Each can be chosen on its own. The Upgrade column is the upgraded-package total in the last two rows.
Assumptions
- Priced for a typical, level Sacramento-area lot. Unusual site conditions are confirmed at the site visit.
- City or County permit and utility fees are confirmed for your address.
- Estimates reflect pricing as of the estimate date and are re-confirmed before contract.
- Agency fees depend on the unit’s size and your property. How California limits impact fees for ADUs of 750 sf or less.